[SOLVED] Problem to update activities - by: QuentinB

$
0
0
Hello,

Sometimes, planned end date is set before the planned start date, which prevent any further update on the concerned activity.
I'm currently using v6.2.5.

Here is a step by step method to generate this bug:
- Create an activity (just set the name, no date). It will appears on the current day (date D) on the planning.
- Run planning calculation a day before (D-1). Planned start and end date will be set to D-1.
- Update the field "handle" on the activity and set it on current date (date D).
- Run again a planning calculation

From here, you got an activity with a start date > end date which cause the bug.


Regards,
Quentin.

How this can be fixed on the interface ? The only known possibility (to me) is to update the field in the database.