Order vs Planned Work for T&M project - by: ade

$
0
0
Hi,

The feature to bill the T&M project is available based on a resource.

Do you have a feature to order T&M effort on a resource? The objective is to declare an order before starting the project : like a baselinework (an order) for the customer.

Example :
° declare a T&M project
* declare an activity
* declare resource
* baseline project
* evaluate the baseline work/cost
* make a T&M order based on resource cost/work

Thx for your answer