The Resource Planning view should indicate which resources are overloaded, by how much and for which period.
I deliberately overloaded a resource, but it does not get highlighted at all.
The planning view shows that the resource is assigned at 120% (see bottom section).
But the tooltip in the top section does not show the overload in red/orange.
The Resource Planning view also fails to highlight the overload situation.
Note that the task bar is shown in green for Task-5.
Finally, I clicked the Calculate activities planning button for the project.
ProjeQtor did not level the resource loading by bringing it down to 100% and making the task duration longer.
I expected the following behavior:
1. In Planning view, the task bar for an overloaded task is shown in orange (instead of green).
2. When we right-click on that task, the overloaded resource's daily work is shown in orange.
3. In Resource planning view, the overloaded resource bar are shown in orange.
4. The Activities planning button brings the overloaded resources back to 100%, and adjusts the task duration.
I deliberately overloaded a resource, but it does not get highlighted at all.
The planning view shows that the resource is assigned at 120% (see bottom section).
But the tooltip in the top section does not show the overload in red/orange.
The Resource Planning view also fails to highlight the overload situation.
Note that the task bar is shown in green for Task-5.
Finally, I clicked the Calculate activities planning button for the project.
ProjeQtor did not level the resource loading by bringing it down to 100% and making the task duration longer.
I expected the following behavior:
1. In Planning view, the task bar for an overloaded task is shown in orange (instead of green).
2. When we right-click on that task, the overloaded resource's daily work is shown in orange.
3. In Resource planning view, the overloaded resource bar are shown in orange.
4. The Activities planning button brings the overloaded resources back to 100%, and adjusts the task duration.