hi all,
We need to change real work allocation unit.
today, we are using "days". We would like to change to hour. so my question is.
what's happend on real work already set in days in our projects ?
is it possible to change this value without issue ?
what will happen to the projects for which the charges are already made in days, and for which future charges will be made in hours ?
could you help me to see more clearly?
Thank's for all.