How to enter backdated tasks, and let ProjeQtor re-schedule the project - by: NarayanAras

$
0
0
I have a small project, as shown below:


The project started and immediately got stalled, so it was not maintained in ProjeQtor.
Then the PM wanted to use ProjeQtor to manage it.

Because of the circumstances, we have to tell ProjeQtor that-
(a) The project actually started in the past
(b) Some of the tasks started on specific past dates,
(c) Certain amount of real work is done in some of those tasks in the past, and

Based on this data, we want ProjeQtor to re-assess the Left work in all tasks, and plan the execution of the remaining part of the project starting from today.

What is the actual method to execute each of these steps?

BTW I tried to enter a past date in the Validated start date column, but that task refuses to jump to that date.
I have ensured that the project's start date is sufficiently back-dated; so that is not the reason for this failure.