Auto calculate assigned (h) for resouce assigned to activity - by: VERP

$
0
0
Hi,
Is there a way to calculate the assigned (h) based on the rate of a resource and the planned days in the activity?
e.g.:
R#1 is assigned to Activity1 for 80%
Activity1 has 20 planned days, the field assigned (h) is not filled automatically

Now I have to calculate manually the assigned hours for each resource, it would be nice if this was pre-calculated.

Kind regards