Hi all,

I'm using Projeqtor 6.3.7

I've just done the following operations on a project.
3 resources on my project. Everyone has entered real work up to 31 october 2018.
On one of the resource, i have just entered a cost (C EUR) on the expert profile (This profile is the one my resource is assigned with for the projet / activity)
There was no other cost in the system for the resource.

On the project before entering the cost, real work was X days and real cost was 0 EUR
I saved the cost for the function of my resource on the project (Expert)
Back to the activity, the real cost is still 0 EUR.

Then I enter 1 day on the real wok allocation screen
Real work is now X+1
And real cost is now C EUR, which is the cost I have just allocated for the function.

Seems like real cost has not change for the already existing work.

Any idea ?
Thanks in advance.
Cyril