Hi
I'm playing with Rate Allocation on projects and Rate assignment on activities.
I'm wondering if Rate is only an information about availability or if Rate is used by planning calculation ?
If Rate is used by calculation, can you explain how ?
Regards
I'm playing with Rate Allocation on projects and Rate assignment on activities.
I'm wondering if Rate is only an information about availability or if Rate is used by planning calculation ?
If Rate is used by calculation, can you explain how ?
Regards