Hi
As far as I know, planned work is calculated by Projeqtor.
For example : Mr X has to work 5 days on a task during 15 days between 05/11/2018 and 24/11/2018 based on the mode "don't start before validated date". Mr X is available 50% for the project and 100% by day for the task.
If I launch planning calculation, Projeqtor fixes date of work :
BUT If I want to fix planned date my self. For example :
More difficult : If I want to fix some planned date my self and let Projeqtor calculates the other dates. For example :
N.B. : I tried to use a meeting to fix date (meeting duration = 1 day) and I linked meeting to the task but Projeqtor ignores time spent in meeting and doesn't decrease left work on task. Therefore, Projeqtor plans 5 days instead 4 days (5 days planned - 1 day in meeting)
Regards
As far as I know, planned work is calculated by Projeqtor.
For example : Mr X has to work 5 days on a task during 15 days between 05/11/2018 and 24/11/2018 based on the mode "don't start before validated date". Mr X is available 50% for the project and 100% by day for the task.
If I launch planning calculation, Projeqtor fixes date of work :
- Monday, Tuesday : 1 day for the week between 05/11/2018 and 09/11/2018
- Wednesday : 0,5 day for the week between 05/11/2018 and 09/11/2018
- Monday, Tuesday : 1 day for the week between 12/11/2018 and 16/11/2018
- Wednesday : 0,5 day for the week between 12/11/2018 and 16/11/2018
BUT If I want to fix planned date my self. For example :
- Monday 05/11/2018 : 0,75 day
- Wednesday 07/11/2018 : 1 day
- Thursday 08/11/2018 : 1 day
- Friday 09/11/2018 : 0,5 day
- Monday 12/11/2018 : 0,5 day
- Thusday 15/11/2018 : 0,75 day
- Monday 19/11/2018 : 0,5 day
More difficult : If I want to fix some planned date my self and let Projeqtor calculates the other dates. For example :
- Wednesday 07/11/2018 : 1 day
- Monday 12/11/2018 : 0,5 day
- Monday 19/11/2018 : 0,5 day
- Projeqtor calculates the 3 left days
N.B. : I tried to use a meeting to fix date (meeting duration = 1 day) and I linked meeting to the task but Projeqtor ignores time spent in meeting and doesn't decrease left work on task. Therefore, Projeqtor plans 5 days instead 4 days (5 days planned - 1 day in meeting)
Regards