[SOLVED] lock planned work - by: apad

$
0
0
Hi
As far as I know, planned work is calculated by Projeqtor.
For example : Mr X has to work 5 days on a task during 15 days between 05/11/2018 and 24/11/2018 based on the mode "don't start before validated date". Mr X is available 50% for the project and 100% by day for the task.
If I launch planning calculation, Projeqtor fixes date of work :
  • Monday, Tuesday : 1 day for the week between 05/11/2018 and 09/11/2018
  • Wednesday : 0,5 day for the week between 05/11/2018 and 09/11/2018
  • Monday, Tuesday : 1 day for the week between 12/11/2018 and 16/11/2018
  • Wednesday : 0,5 day for the week between 12/11/2018 and 16/11/2018
I'm fine with that. It's OK.

BUT If I want to fix planned date my self. For example :
  • Monday 05/11/2018 : 0,75 day
  • Wednesday 07/11/2018 : 1 day
  • Thursday 08/11/2018 : 1 day
  • Friday 09/11/2018 : 0,5 day
  • Monday 12/11/2018 : 0,5 day
  • Thusday 15/11/2018 : 0,75 day
  • Monday 19/11/2018 : 0,5 day
Is there a way to do that ? If Yes, tell me how.

More difficult : If I want to fix some planned date my self and let Projeqtor calculates the other dates. For example :
  • Wednesday 07/11/2018 : 1 day
  • Monday 12/11/2018 : 0,5 day
  • Monday 19/11/2018 : 0,5 day
  • Projeqtor calculates the 3 left days
Is there a way to do that ? If Yes, tell me how

N.B. : I tried to use a meeting to fix date (meeting duration = 1 day) and I linked meeting to the task but Projeqtor ignores time spent in meeting and doesn't decrease left work on task. Therefore, Projeqtor plans 5 days instead 4 days (5 days planned - 1 day in meeting)


Regards