Hello,
I have a team of 4 ressources. They manage 158 projects.
They have made the WBS with either fixed and floating milestones.
To proceed so In addition of the fixed delivery date, I've made a priority list for the "ASAP" projects.
So I now know the estimative delivery date of all the projects. It's GREAT.
But, with new weeks comes new projects.
Does ProjeQt'Or give a tool to "insert" a new project in the planning ?
Or more concrete how do I proceed to "insert" new projects with the best choice of the ressource ?
For the moment, I think that I must extract the floating milestone project list of each ressource and set the new project priority.
Then, I have to ask the ressource to run the planning with the new project to have the best calculated delivery date.
Have to do the same with all the ressource and choose the one with the best delivery date.
Is this solution the only one existing in ProjeQt'Or ?
Thanks for your help.
A ProjeQt'Or fan.
I have a team of 4 ressources. They manage 158 projects.
They have made the WBS with either fixed and floating milestones.
To proceed so In addition of the fixed delivery date, I've made a priority list for the "ASAP" projects.
So I now know the estimative delivery date of all the projects. It's GREAT.
But, with new weeks comes new projects.
Does ProjeQt'Or give a tool to "insert" a new project in the planning ?
Or more concrete how do I proceed to "insert" new projects with the best choice of the ressource ?
For the moment, I think that I must extract the floating milestone project list of each ressource and set the new project priority.
Then, I have to ask the ressource to run the planning with the new project to have the best calculated delivery date.
Have to do the same with all the ressource and choose the one with the best delivery date.
Is this solution the only one existing in ProjeQt'Or ?
Thanks for your help.
A ProjeQt'Or fan.