Hi,
Currently working on version v5.2.5, I have many tasks that failed to be scheduled probably for many different reasons...
Except the message alert when doing planning calculation and the "red day" in assignation part of one activity, is there a quick way to find tasks that are not really scheduled ?
In fact I have some tasks appearing in purple when not completely scheduled, but I have also some tasks not appearing at all !
Could it be an idea to make appear this kind of info in reports such "monthly planning resource/project" ?
Thx
Currently working on version v5.2.5, I have many tasks that failed to be scheduled probably for many different reasons...
Except the message alert when doing planning calculation and the "red day" in assignation part of one activity, is there a quick way to find tasks that are not really scheduled ?
In fact I have some tasks appearing in purple when not completely scheduled, but I have also some tasks not appearing at all !
Could it be an idea to make appear this kind of info in reports such "monthly planning resource/project" ?
Thx