That's possibly a stupid question, but I could not really find an answer so far in the online manual. Points to the correct docs are appreciated.
How can I deal with Acitivities which will only take about a few hours at most?
Are Activities supposed to be larger chunks of work? If so, how do I model small "Activities" in ProjeQtor?
I currently modelled several Activities which will only take about an hour or slightly longer, far from a whole day. However I don't seem to be able switch the "duration" input boxes to "hours", they always state "days". I was only able to switch the work allocation boxes from days to hours, but this didn't have any effect on the estimated duration entry boxes.
In this forum I read about the possibility to work with half-day activities at least, but I also cannot figure out how to do this. The input box does not accept "0.5" and while I can enter "0,5", this will be interpreted as "0" by ProjeQtor, which is clearly not what I intended it to be...
Another question which doesn't get clear from the manual: If a lower Activity priority value "more important" or a higher one?
Everywhere it's stated that Activity planning is done according to priority values, but I couldn't find a single place which actually explains how the priorities are supposed to be used.
And while I already played with ProjeQtor for quite a while now, my modelled Projects / Activities are not yet sufficiently fleshed out such that I could just try it with the integrated planner. This will probably still take a while until I get to the point that I can actually press this button...
How can I deal with Acitivities which will only take about a few hours at most?
Are Activities supposed to be larger chunks of work? If so, how do I model small "Activities" in ProjeQtor?
I currently modelled several Activities which will only take about an hour or slightly longer, far from a whole day. However I don't seem to be able switch the "duration" input boxes to "hours", they always state "days". I was only able to switch the work allocation boxes from days to hours, but this didn't have any effect on the estimated duration entry boxes.
In this forum I read about the possibility to work with half-day activities at least, but I also cannot figure out how to do this. The input box does not accept "0.5" and while I can enter "0,5", this will be interpreted as "0" by ProjeQtor, which is clearly not what I intended it to be...
Another question which doesn't get clear from the manual: If a lower Activity priority value "more important" or a higher one?
Everywhere it's stated that Activity planning is done according to priority values, but I couldn't find a single place which actually explains how the priorities are supposed to be used.