Hi,
I am new to this software. I have two questions. Please help.
(1) After creating the tasks list, to record the progress, I am filling the timesheet. Is it the correct way of recording progress of work?
(2) In the above method, actually I am recording the % of planned days utilized and on the Gantt Chart % progress comes accordingly. Is there a way to actually record progress of actual work? Example : If I have already worked for 50% of days, but actually work has progressed for 30% only, can I show on Gantt Chart progress as 30% thus reflecting true progress?
Thanks in advance.
I am new to this software. I have two questions. Please help.
(1) After creating the tasks list, to record the progress, I am filling the timesheet. Is it the correct way of recording progress of work?
(2) In the above method, actually I am recording the % of planned days utilized and on the Gantt Chart % progress comes accordingly. Is there a way to actually record progress of actual work? Example : If I have already worked for 50% of days, but actually work has progressed for 30% only, can I show on Gantt Chart progress as 30% thus reflecting true progress?
Thanks in advance.