planification calculation question - by: pipobru

$
0
0
Hello, I would help the project with my contribution (tests) Very thanks for your job, for me the better tools for manage projets !

My context:
A pool with ghost ressources
tasks on project without dependency or other contraints

My questions:
why in summary of availabilities repport i have number of days planned and not number of days remaining planable (number of ETP * number of working day-number of days planned),
I understand your previous answer on this subject, but i propose to add this information perarps with a different color ?
Why for each days the full pool capacity are not planed ? (all task have no contraint (start date, dependance, ...)

For explain my test see screens shoots in attachement.