Minor question:
I noticed that the manner in which real work is logged differs between Tickets and Meetings - is that expected behaviour ? (I don't see any impact, but it's not very consistent).
- Create ticket T1 , with planning activity = A_TCK
- Create periodic meeting PM1, with planning activity = A_MEET
- Log work on T1 and on PM1#1
- Run report "detailed work per resource":
=> the real work on Ticket is displayed as work on the planning activity A_TCK
=> the real work on Ticket is displayed as work directly on the meeting, without mention of the planning activity A_MEET
(see attached)
As I said, very minor, but maybe for consistency of future developments it would be best to standardize the approach (in table 'work', use refType = 'Activity' and idWorkElement to refer to the meeting).
Note : saw this in the V5 I'm using, but tested the same on V6.
I noticed that the manner in which real work is logged differs between Tickets and Meetings - is that expected behaviour ? (I don't see any impact, but it's not very consistent).
- Create ticket T1 , with planning activity = A_TCK
- Create periodic meeting PM1, with planning activity = A_MEET
- Log work on T1 and on PM1#1
- Run report "detailed work per resource":
=> the real work on Ticket is displayed as work on the planning activity A_TCK
=> the real work on Ticket is displayed as work directly on the meeting, without mention of the planning activity A_MEET
(see attached)
As I said, very minor, but maybe for consistency of future developments it would be best to standardize the approach (in table 'work', use refType = 'Activity' and idWorkElement to refer to the meeting).
Note : saw this in the V5 I'm using, but tested the same on V6.