The 45° curve does not permit to have projection of the curve.
I mean, the curve shall show the last miletone. x axe and y axe shall have the same date. If a milestone shift, we have to see the curve whick shif and also the projection until the end date....We don't have this projection. The last date on x axe is the date of the update milestone. We have to show also the date of the end of the project (corresponding to the last miletone) ....same of the y axe.
attached an example with a project whom in y axe is the 02/12/2016 but in the y axe is the 30/11/2016 for "test 2" milestone. The axe must be flat afeter the "update date"......
I mean, the curve shall show the last miletone. x axe and y axe shall have the same date. If a milestone shift, we have to see the curve whick shif and also the projection until the end date....We don't have this projection. The last date on x axe is the date of the update milestone. We have to show also the date of the end of the project (corresponding to the last miletone) ....same of the y axe.
attached an example with a project whom in y axe is the 02/12/2016 but in the y axe is the 30/11/2016 for "test 2" milestone. The axe must be flat afeter the "update date"......