Hello
I wish you an happy new year![:-) :-)]()
I migrated to ProjeQtOr v6.0.5, from a database version v5.4.5 (yes, a bit old...). There weare 46 errors / warnings.
My project seems good but satursdays and sundays are now work days : could you tell me how to get them simply back to days off as they were before the migration ?
In environmental parameters / diary, I have one diary called "default" where I had written the other days off (public holidays = "jours fériés"). I could do the same with satursdays and sundays, for the 2 years of my project but it's a bit boring![;-) ;-)]()
Thank you for your help.
PS : thank for having added in the new version the report I suggested "work plan per month and per resource" (that is where I found my resources work all days of the month
)
I wish you an happy new year

I migrated to ProjeQtOr v6.0.5, from a database version v5.4.5 (yes, a bit old...). There weare 46 errors / warnings.
My project seems good but satursdays and sundays are now work days : could you tell me how to get them simply back to days off as they were before the migration ?
In environmental parameters / diary, I have one diary called "default" where I had written the other days off (public holidays = "jours fériés"). I could do the same with satursdays and sundays, for the 2 years of my project but it's a bit boring

Thank you for your help.
PS : thank for having added in the new version the report I suggested "work plan per month and per resource" (that is where I found my resources work all days of the month