poject: version product - by: dep@eca.fr
I have 2 times the linked products and 2 times the project versions linked on the page of a project
View ArticleGenerating PDF for Ticket Does Not Work - by: gohrner
Apparently I misconfigured something, but I have not idea what. I'm playing with a fresh install of ProjeQtor 7.4.3. I created an example Ticket, added some notes, closed and reopened it some times,...
View Articlee-mail automatique aux équipes et responsables - by: noel-a
Bonjour, Je reçois depuis peu ces messages : [ProjeQtOr] Certaines de vos ressources n'ont pas saisi leur suivi correctement jusqu'au 18/01/2019[/u] Utilisant pour le moment Projeqtor seul, je ne veux...
View Article[SOLVED] Decimal numbers in Report - by: clarezoe
Hi, I generated a report of a global planning project&resource per month, however, some of the numbers are not integer numbers, like 49.999, 30.001. I don't know where they are coming from because...
View ArticleSearch information about the functionnality "Catalog" - by: dnaton
Hello, I'm looking for some information about the functionnality "Catalog" (Finacial\Incomes\Catalog) : concepts, how it works, relationships with client quotations or order,... I searched in online...
View ArticleMultiple allocation of ressource - by: CRAMIF_PMO
Hello, How can I allocate 1 ressource (1 user) to all the projects in one and unique operation (instead of doing it on each project) ? Thanks for your answer Jean-Christophe
View ArticleActivity priority - by: Lee
Hi, I have project, subproject. Only Subproject have activity. I try to prioritize activity from all of the project and other project, but it does not work. All activity have same characteristics, and...
View ArticleEmail on event for all activity sons of a given Project - by: Gaspard
Hello everyone, I have to find if it's possible to make an "Email on event" every time an activity status change. With an image to illustrate it'll be easier to understand : So I'd like that everytime...
View Articleprojeqtor configuration - by: Dzahli
I work as an IT support and for a good reason with the amount of clients walking in and out of our office during working ours is kind of frustrating and for this reason we decided to get a ticket...
View ArticleError when saving Timesheet - by: karl.binet
Hi, V7.4.2 On monday, february 25, a user entered time into is Timesheet and when he saved, received an error Look at the log file and saw this error 2019-02-25 09:44:12.612 ===== TRACE ===== WARNING -...
View ArticleBind own defined roles to mail receivers - by: SKOROSI
We have created own workflows and we defined the roles for them. I would like to ask you if is possible to bind own roles with mail on events - mail receivers. Feature mail on events contains only a...
View ArticleV8.0.0 is now available as Release Candidate - by: Gautier
New V8.0.0 has been deployed as Release Candidate. It brings three major changes, some expected for long. Modules management ( It allows to enable or disable Modules as Time tracking, Financial, Risks,...
View ArticleTimesheet - by: dep@eca.fr
Normally (on V7.4.4) 10hours per day and ETP 0.8(projetleader) and 0.74 (member,) so the color was black until 7.4 ( color turn green) for member and until 8 (color turn green) for projectleader, if...
View ArticleAbility to have multiple view for project, activity, tickets,... - by: dnaton
Hello, A suggestion for a future version of ProjeqTor : possibility to have more than one view, There is a lot of colums but we can't display all what we sometimes need. Ok, it's easy to modify the...
View ArticleCreate Emails on event automatically - by: Gaspard
Hello everyone, I have to develop projeQtor, and because it's a very large program, I woud ask your help to find out some function in the code that you might know the name. The global idea is : when...
View ArticleRessource Planning - by: dep@eca.fr
On new version V8.0.0, when I change ressource or team, nothing happen! no refresh screen.
View ArticleTime posted in tickets not visible on reports - by: Apercie
Hello, I would like to use tickets in order to declare time for some kind of "activities". However, it seems that this time is not showing in the various reports. Is there a way that it is taken into...
View ArticleProjeqtor Database - link between the two tables "activity" and "work" - by:...
Hi everybody, I'm trying to extract the worktime consumed per ressource and per project through this SQL code below, and it works fine. SELECT r.`fullname`, p.`name`, year(workDate), month(workDate),...
View ArticleCustomizing for Construction industry - by: mpvshameem
Is there any way to customize for the Construction industry. I would like to assign subcontractor to the activity
View ArticleProgress and timesheet - by: dieperie
Hi, I run a complex project with many tasks and where many different stakeholders are involved with minimal FTE each. The second complexity is related to individual timesheet tracking. Despites many...
View Article