Why the progress of risk over 100% ? - by: robertji
hi Why the progress of risk could over 100% ?
View ArticleClone Environtment - Only for selected projects - by: javierrm
Is posible include on the popup windows to create the clone environment a list with all projects, and then we can select the projects to include on the environment cloned. It'ss posible or are planned...
View Article[SOLVED] How to automatically sent warnning mail? - by: robertji
Hi, Do the system could automaticlly send the warnning mail (indicator: respect of validated start date) without login ? thanks alot!
View ArticleUninstall a plugin - by: antoine1003
Hey, I am looking to uninstall a plugin properly (remove column added, reset uploaded file, etc..). This feature doesn't seem to be implemented, am I right? When we install a plugin it's for ever ? Is...
View ArticleHR Module - by: mcanuto
Hello, I've discovering the HR Module, that we were waiting for, but I can't understand some of the concepts: * What's the difference between a "Manager of employee's leaves" and a "Manager of...
View ArticleLeave Manager cannot create leave periods (when he's not his own leave...
Hello, I defined a hierarchie where : Ressource 1, 2 and 3 are employees. Ressource 1 is Leave Manager of himself and Ressource 2. Ressource 2 is Leave Manager of Ressource 3. The problem is that...
View ArticleCreating tickets from a mail - by: lsigroup
Hi, I'm currently asked to think about a way to create tickets (probably to be reviewed after their creation) automatically in our ProjeQtOr from incoming mails on a mailbox exclusively used for this....
View Article[SOLVED] Change requests not available in list of linked elements - by: TheCube
v8.3.2: When inserting a linked element the list does not show "Change Requests".
View ArticleClose a activity with more to do? - by: rakoun
Hello, I have a question about 'projeqtor'. When I marked a activity to "done", this activity is taken into account when I recalculate the project. Why? Do I need to mark this activity to "close" so it...
View Article[SOLVED] How to delete duplicate report - by: Rand
Hi, I don't know why but 2 of my reports was duplicated during the migration to the newer version. I searched for a while in the files but i find out nothing. Do you know in which file i can search in...
View ArticleAutoload project's parent activity within a ticket - by: fmartin
Good morning, I'd like to know if you could add the possibility to autoload the parent activity of a project within a ticket ? The master filter is on "All projects" (left top corner), and you enter a...
View ArticleProblem displaying icons in report - by: Rand
Hi, I encountered a problem with the display of icons in report. Some icons are well displayed otherwise others not. Here are the screenshots
View Article[SOLVED] Close a activity with more to do? - by: rakoun
Hello, I have a question about 'projeqtor'. When I marked a activity to "done", this activity is taken into account when I recalculate the project. Why? Do I need to mark this activity to "close" so it...
View Article[SOLVED] Problem displaying icons in report - by: Rand
Hi, I encountered a problem with the display of icons in report. Some icons are well displayed otherwise others not. Here are the screenshots
View ArticleHow do I prevent members of a project from rolling down Projects board up...
My problem: After many configurations I think I got the access rights for members of one project correct. But up left is a roll down thing which shows all my projects. How do I stop the members of this...
View ArticleIncoming Issue - by: karl.binet
Hi, V8.3.3, In the incoming windows, the value in "impact work" seem to be rounded in days if i enter 40 hours, when we hit save the value is changing to 37,5 hours. Expected behavior: keep efforts in...
View Articlehelp - by: akyolselinay
Hello, I started to learn Projeqtor, I just started business life and we need to use this program actively. I have no idea about this and my English is very weak. I signed up from the registration...
View ArticleOrganisation of QUESTIONS and DECISION into planning - by: ashofphoenix
Hi, - Is there a way to better organise Questions and Decisions into the planning ? The problem is that I've got some specific "management" task in order to organise my planning but I can't put all...
View Article[SOLVED] Incoming Issue - by: karl.binet
Hi, V8.3.3, In the incoming windows, the value in "impact work" seem to be rounded in days if i enter 40 hours, when we hit save the value is changing to 37,5 hours. Expected behavior: keep efforts in...
View ArticleInvalid controls. (Activities) - by: Cjaxen
Hello all, I am playing around on a fresh install, and I'm not sure if I've set something wrong or what not, but not able to create an Activity. I only have 1 project, 1 task attached to it. When I try...