Hi,
I face a regular issue when working on periodical meeting on version 5.2.5. When updating one meeting with its "compte-rendu", I don't change its status as one resource has not filled in the workload. I then update the workload and when I come back to meeting list, I don't see it anymore as it has moved to "canceled" without any action from me on status
. See history bellow
I face a regular issue when working on periodical meeting on version 5.2.5. When updating one meeting with its "compte-rendu", I don't change its status as one resource has not filled in the workload. I then update the workload and when I come back to meeting list, I don't see it anymore as it has moved to "canceled" without any action from me on status
. See history bellow